A price for “fitting the steel” can stop when the beam is in position. Another builder may include fire protection, plaster repairs and disposal. Before comparing either price, ask each builder to mark the start and end of their work on the same drawing revision.
Turn a day rate into a comparable allowance
Suppose a contractor quotes £280 per person per day for two people and estimates two days. That gives 2 × 2 × £280 = £1,120 for labour. If the same contractor quotes £300 for plant, the allowance becomes £1,420 before tax. These invented figures illustrate billing units. They aren’t UK rates, a crew recommendation or a forecast of the time your job will take.
Now suppose a second contractor quotes a fixed £1,550 on the same tax basis, including plant and waste removal. The apparent gap is £130. To compare them, find out what waste removal would cost under the first quote and what each contract says about an extra day. For the first quote, one additional day for the same two people adds £560 in labour before any extended plant hire.
Mark the gaps on the quotation
| Item to check | What to ask the contractor to write down |
|---|---|
| Steel delivery | Who books the slot and who unloads the vehicle? |
| Site preparation | Which rooms, floors and existing finishes are protected? |
| Temporary works and lifting | Who provides the design, equipment and competent supervision? |
| Completion | Which connections, specified fire protection, inspections and repairs are included? |
| Extra work | Who can authorise it and how will labour and equipment time be recorded? |
Ask who pays if an agreed delivery slot is missed or the issued drawings change. Keep allowances for unknown work separate from a fixed quote. An excluded item with no price yet belongs on the list of open questions.
Keep design fees and site labour separate
A permanent design appointment doesn’t automatically cover temporary works. The contractor needs an agreed plan and named responsibilities before the alteration starts. See HSE’s explanation of temporary works and the engineering fee comparison.
Once the scope is agreed, add the gross labour package to the project budget calculator. If the builder’s package already includes the steel supply or plant, enter that cost only once. Keep the drawing, written exclusions and any later instructions with the price.