Skip to content

How long does RSJ installation take and when can you use the room again?

Separate steel delivery from the time your room is out of use. Take a sample RSJ programme to your builder and record who confirms each date.

If a builder quotes “one day for the steel”, ask when you can use the room again. The steelwork crew might finish on Friday while the kitchen still has no power, exposed work is awaiting inspection or the room is closed for making good. Ask the builder to put two dates against the room itself: when you must clear it and when they expect to hand it back for use.

Separate design from site time

The fabricator can usually explain its lead time quite precisely once it has the information it needs. Ask what starts the clock. Is it receipt of the deposit, written acceptance of the cut list or release of a particular drawing revision? Record that condition next to the delivery estimate. “Ten working days from approval” gives you very little to book against until someone confirms which approval and when it happened.

Agree separately what “usable” means at your address. In a kitchen it might mean safe access, working sockets and a connected sink, with decoration to follow. In a through-lounge it might mean being able to reach the stairs each evening. Write down what the household needs before agreeing the dates.

A programme to fill in with your builder

This fictional kitchen example shows what a confirmed date looks like alongside an open question. The dates illustrate the paperwork for one enquiry. Enter your team’s own dates in the last column when you copy it.

Example programme for a kitchen opening
MilestoneWho confirmsWhat must be readyAgreed date or status
Steel released for fabricationEngineer and fabricatorIssued schedule received and drawing revision agreed2 February, revision B acknowledged
Steel deliveredStockholder and site contactCut list accepted, vehicle access and unloading agreed12 February, morning slot booked
Kitchen out of useBuilder and householdSite arrangements, access for occupants and service interruptions agreedOpen, builder to confirm
Work available for inspectionBuilder and building control contactRequired stage identified and visit arranged where neededOpen, visit to be booked
Kitchen returned to useBuilder and relevant tradesAccess and agreed services restored, outstanding finishes listedOpen, confirm sink and sockets

In the example, 12 February is a delivery appointment. It gives the household no confirmed date for emptying the kitchen. Before taking time off work, ask who will tell you when those last three entries change.

Agree hold points

Ask the contractor who manages temporary works and who authorises the next stage. Record any inspection that must take place while work is visible. A date in a homeowner’s programme cannot determine when temporary support can be altered or removed. HSE guidance on temporary works · GOV.UK building regulations approval.

Track revisions and handover

Suppose the engineer issues revision C after the fabricator has acknowledged B. Ask the fabricator which pieces are affected and whether the booked delivery still stands. Have the builder update the room closure, inspection and handback entries separately. That tells you whether the changed drawing affects the family’s arrangements as well as the steel order.

At handover, keep the final drawing, inspection or completion records supplied for the job, and a dated list of outstanding finishes. The installation checklist covers what to keep before, during and after the work.