A higher steel quote doesn’t tell you which part of the order became dearer. Start with the two written offers. Put the drawing revision and expiry date at the top of each, then line up the charged metres, the rate, fabrication and transport. You can then ask the supplier about a specific difference.
Trace a £122 change
Suppose both offers cover 10 m of the same section. They are invented for this exercise, in pounds before VAT. The second drawing adds a pair of connection plates.
| Item | First offer | Revised offer | Change |
|---|---|---|---|
| Bare steel | 10 m × £52 = £520 | 10 m × £54 = £540 | +£20 |
| Fabrication | £80 | £170 | +£90 |
| Delivery | £60 | £72 | +£12 |
| Total | £660 | £782 | +£122 |
Only £20 of the £122 increase is accounted for by the higher quoted steel rate. The £90 fabrication change is the first line to discuss. Ask whether it covers both plates, drilling and the specified finish. Confirm that the earlier £80 of fabrication is still included. A change to one merchant’s price per metre is also insufficient evidence of a market-wide price rise.
When the quantity changes as well
Keep the old rate and apply it to the revised quantity first. That isolates the cost of buying more steel. For example, moving from 10 m at £52 to 12 m at £54 adds £128 on the goods line. Of that, £104 is two extra metres at the old rate. The other £24 is the £2 rate change across the new 12 m. This calculation only makes sense if the section and price basis are the same.
Before accepting a revised price
Check what date the offer expires and whether acceptance fixes price, reserves stock or depends on a further order acknowledgement. Record who is paying delivery and unloading and whether the offer includes VAT. Keep net values together during the comparison. GOV.UK lists the UK VAT rates. The supplier should state the treatment of the actual order.
If the design is still being revised, ask the fabricator what lead time they need once the drawings are issued. Buying the wrong cut length early can cost more than the quoted increase. Transfer the accepted lines into the project budget calculator and keep a dated copy of the offer. This page uses illustrative quotations and supplies no price forecast.