Building Control Approval Process for RSJ Installations – Complete UK Guide 2026

Step-by-step guide to obtaining Building Control approval for RSJ beam installations in the UK. Requirements, fees, inspection process, and common pitfalls for 2026.

Building Control Approval Process for RSJ Installations – Complete UK Guide 2026

Installing an RSJ (Rolled Steel Joist) beam in any load-bearing capacity requires formal Building Control approval in the UK. This isn’t optional – it’s a legal requirement under the Building Regulations 2010. Failure to obtain proper approval can result in enforcement action, difficulty selling your property, insurance invalidation, and potentially dangerous structural issues.

This comprehensive guide walks you through the entire Building Control approval process for RSJ installations in 2026, including requirements, costs, timelines, and what to expect at each stage.

Why Building Control Approval is Mandatory

Legal Requirements: Under Building Regulations Part A (Structure), any work that affects the structural integrity of a building requires approval. This includes:

  • Installing new RSJ beams for openings
  • Removing load-bearing walls
  • Loft conversions with structural alterations
  • Extensions requiring beam support
  • Garage conversions with structural work

Consequences of Non-Compliance:

  • Enforcement notices requiring removal or rectification
  • Fines up to £5,000 plus daily penalties
  • Property sale issues – solicitors will request certification
  • Insurance invalidation – claims may be refused
  • Mortgage problems – lenders may refuse or recall loans
  • Safety risks – unchecked work may be structurally unsound

Two Routes to Approval

1. Local Authority Building Control (LABC)

Your local council’s Building Control department handles applications directly.

Advantages:

  • Familiar with local building stock and conditions
  • Direct communication with your council
  • Can provide pre-application advice
  • May be more flexible on minor variations

Disadvantages:

  • Can be slower (4-6 week plan approval typical)
  • Limited evening/weekend inspection availability
  • Fees non-refundable even if work doesn’t proceed

Typical Fees (2026):

  • Full Plans application: £300-500
  • Building Notice: £250-450
  • Regularisation (retrospective): £500-800

2. Approved Inspector (Private Building Control)

Independent companies approved by the Construction Industry Council.

Advantages:

  • Faster service (2-3 week plan approval typical)
  • More flexible inspection times
  • Can work across council boundaries
  • Often more responsive communication

Disadvantages:

  • Slightly higher fees in some cases
  • Need to register with local authority
  • Must switch back to LABC if inspector goes out of business

Typical Fees (2026):

  • Similar to LABC: £350-550 for standard RSJ installation

Application Methods

Submit detailed plans and calculations before work begins.

Required Documents:

  1. Structural calculations – from chartered structural engineer (CEng MIStructE)
  2. Drawings – plans, elevations, sections showing:
    • Existing and proposed layouts
    • Beam locations and sizes
    • Support details (padstones, bearings)
    • Temporary works arrangements
  3. Application form – completed with all property details
  4. Fee payment – varies by authority
  5. Fire safety strategy (if required)

Timeline:

  • Submission to approval: 5 weeks statutory (can be extended to 8 weeks with agreement)
  • Practical reality: 3-6 weeks typical in 2026

Advantages:

  • Work cannot start until approved
  • Plans are checked in detail
  • Any issues identified before work begins
  • Provides certainty for contractors

Building Notice

Simpler notification without detailed plans upfront.

Process:

  • Submit basic notice at least 2 days before work starts
  • Provide structural calculations when requested
  • Inspector checks work on site during inspections

When to use:

  • Smaller, straightforward projects
  • Working with experienced contractor who knows requirements
  • Time is critical and engineer calculations already obtained

Risks:

  • Inspector may require changes mid-project
  • Can cause delays and additional costs
  • Less certainty about final approval

Regularisation Certificate (Retrospective)

For work already completed without approval.

Process:

  • Submit application with photos and details of work done
  • Inspector assesses what can be seen
  • May require opening up work for inspection
  • May require additional calculations or strengthening

Costs:

  • Fees typically double normal charges (£500-800)
  • Potential additional work if issues found
  • May require significant remediation

Important: Some work cannot be regularised if it cannot be adequately inspected. Always get approval before starting.

The Approval Process Step-by-Step

Actions:

  1. Contact Building Control for informal advice
  2. Discuss proposed work and likely requirements
  3. Clarify fees and timelines
  4. Check for any local planning requirements

Cost: Usually free or £50-100

Time: 1-2 weeks for response

Stage 2: Obtain Structural Calculations

Actions:

  1. Engage chartered structural engineer
  2. Provide site details, proposed opening size, loads above
  3. Receive calculations and beam specification
  4. Obtain drawing showing beam location and support details

Cost: £350-600 typical for domestic RSJ installation

Time: 1-2 weeks

Stage 3: Submit Application

Actions:

  1. Complete application form (online or paper)
  2. Attach all required documents
  3. Pay application fee
  4. Submit to Building Control or Approved Inspector

Checklist:

  • Application form fully completed
  • Structural engineer’s calculations
  • Drawings (plans, elevations, sections)
  • Site location plan
  • Fee payment
  • Any additional information (party wall agreements, etc.)

Time: 1 day (submission takes minutes online)

Stage 4: Plan Review

What happens:

  • Building Control reviews your submission
  • Checks compliance with Building Regulations
  • May request additional information or clarifications
  • Sends approval notice or rejection with reasons

Typical queries:

  • Clarification on temporary support arrangements
  • Additional details on padstone specifications
  • Fire protection requirements
  • Ventilation or other matters if work affects these

Time: 3-6 weeks (5 weeks statutory maximum)

Stage 5: Approval Notice Received

Next steps:

  1. Receive formal approval (or conditional approval)
  2. Address any conditions before starting work
  3. Notify Building Control at least 2 days before commencement
  4. Arrange inspection schedule

Important: Approval is valid for 3 years. Work must start within this period.

Stage 6: Work Commences – Required Inspections

Mandatory inspection points for RSJ installation:

1. Foundation/Support Inspection (if new padstones)

  • Before pouring concrete or installing padstones
  • Inspector checks bearing capacity and depth
  • Usually 1 day notice required

2. Before Covering Up

  • After beam installed but before boxing/plastering
  • Inspector checks beam size, position, bearings
  • Verifies compliance with approved drawings
  • Critical – cannot cover work until inspected

3. Completion Inspection

  • After all work finished
  • Final check of installation
  • Verification of fire protection (if required)

Booking inspections:

  • Call or email 1-2 days before required
  • Confirm exact work completed
  • Ensure site accessible and safe

Failed inspections:

  • Work may need to be corrected
  • Re-inspection required (may incur additional fee)
  • Can delay project significantly

Stage 7: Completion Certificate

Final steps:

  1. All inspections passed
  2. Building Control issues Completion Certificate
  3. Certificate confirms compliance with Building Regulations
  4. Keep certificate permanently with property deeds

Time to receive: 2-8 weeks after final inspection (can chase if delayed)

Importance: Essential for property sales. Without it, purchasers’ solicitors will raise queries that can delay or derail sales.

Common Issues and How to Avoid Them

Issue 1: Delayed Plan Approval

Causes:

  • Incomplete submissions
  • Inadequate calculations
  • Missing drawings or details

Solutions:

  • Use pre-application service to clarify requirements
  • Ensure engineer provides comprehensive calculations
  • Submit all documents at once
  • Follow up weekly if approaching statutory deadline

Issue 2: Changes During Construction

Causes:

  • Site conditions differ from assumptions
  • Contractor suggests alternative approach
  • Beam size unavailable, substitution needed

Solutions:

  • Contact Building Control immediately
  • Submit amendment if significant change
  • Get written approval before proceeding
  • Do not deviate from approved plans without consent

Issue 3: Failed Inspections

Causes:

  • Wrong beam size installed
  • Inadequate bearing length
  • Incorrect padstone specification
  • Fire protection missing

Solutions:

  • Contractor should know requirements from approved plans
  • Builder must attend inspections with inspector
  • Rectify issues immediately when identified
  • Don’t cover work until inspection passed

Issue 4: Missing Completion Certificate

Causes:

  • Inspector not notified of completion
  • Minor snags not addressed
  • Paperwork not processed

Solutions:

  • Formally notify completion in writing
  • Chase certificate 2 weeks after final inspection
  • Escalate to Building Control manager if delayed beyond 4 weeks
  • Keep all correspondence and inspection records

Costs Summary (2026)

Building Control Fees:

  • Full Plans: £300-500
  • Building Notice: £250-450
  • Approved Inspector: £350-550

Structural Engineer:

  • Calculations and drawings: £350-600

Temporary Works:

  • Acrow props hire: £40-80 per week
  • Needles, strong boys: £100-200

Total typical cost for approval process: £700-1,200

This is in addition to beam and installation costs (typically £1,500-3,500 for a standard domestic knockthrough).

Tips for Smooth Approval

  1. Engage professionals early – structural engineer and Building Control
  2. Submit complete applications – avoid delays from missing information
  3. Book inspections proactively – don’t wait until last minute
  4. Keep records – all correspondence, approvals, inspection confirmations
  5. Don’t deviate from plans – get approval for any changes first
  6. Communicate – keep Building Control informed of progress
  7. Plan for contingency – allow 2-4 weeks buffer in project timeline

Scotland, Wales, and Northern Ireland

Scotland:

  • Similar system but called Building Warrant
  • Apply to local Building Standards department
  • Fees and process comparable

Wales:

  • Identical to England (Building Regulations 2010 apply)
  • Some local authorities offer Welsh language services

Northern Ireland:

  • Building Control function of District Councils
  • Building Regulations (Northern Ireland) 2012 apply
  • Similar requirements but different forms

Frequently Asked Questions

Q: Can I start work before approval? A: No. Starting work before approval is illegal and may result in enforcement action.

Q: What if I’m just replacing an existing beam? A: Still requires approval unless like-for-like replacement with no structural changes.

Q: Do I need planning permission as well? A: Usually no for internal alterations, but check if property is listed or in conservation area.

Q: Can I DIY or must I use a contractor? A: You can DIY but must still comply with Building Regulations and get professional structural design.

Q: How long is approval valid? A: 3 years from date of approval. Must start work within this period.

Conclusion

Building Control approval for RSJ installations is not just bureaucracy – it ensures your structural work is safe, compliant, and won’t cause problems when selling your property. The process is straightforward if you:

  1. Engage a structural engineer for calculations
  2. Submit complete applications with all required information
  3. Notify Building Control at required stages
  4. Allow inspections before covering work
  5. Maintain communication throughout

Budget £700-1,200 and 6-10 weeks for the complete approval process from first submission to completion certificate. While this adds cost and time to your project, it provides certainty, safety, and protects your property’s value.

Always obtain Building Control approval before installing RSJ beams – the consequences of not doing so far outweigh the modest time and cost involved.

This guide provides general information for England and Wales as of 2026. Always consult your local Building Control authority for specific requirements and current fees.