Knocking Through a Wall: RSJ Installation Guide for Open-Plan Living (With Photos)
Creating open-plan living space by removing a wall is one of the most transformative home improvements. Installing an RSJ steel beam enables you to safely remove load-bearing walls while maintaining structural integrity. This guide covers design considerations, beam selection, installation procedures, costs, and Building Regulations for creating your ideal open-plan space in 2026.
Planning Your Knockthrough
Determining if Wall is Load-Bearing
Signs wall IS load-bearing:
- Runs perpendicular to floor joists
- Walls directly above/below on other floors
- Central spine wall (typical in terraced houses)
- Thick wall (>150mm typically)
- Original building plans show as structural
Signs wall is NON-load bearing:
- Thin partition (<100mm)
- Parallel to floor joists with no walls above
- Recent addition not on original plans
- Stud wall construction
If uncertain: Hire structural surveyor (£150-300) - never guess!
Design Considerations
Size of opening:
- Full wall removal (typical 3-5m)
- Partial removal with piers/columns at ends
- Multiple openings with intermediate supports
What stays, what goes:
- Floor to ceiling removal (maximum space)
- Retain bottom section for services/storage
- Keep partial walls for structural/aesthetic reasons
Services relocation:
- Electrical (rewire before demolition)
- Plumbing (reroute pipes)
- Heating (radiator relocation)
- Cost: £500-1,500 for services
Beam Selection by Project Type
Small Knockthrough (2.5-3.5m)
Typical scenario: Victorian terrace, combining living/dining rooms
Configuration:
- Span: 3.5m
- Solid brick walls (215mm)
- Floor joists parallel to wall (no load transfer)
- Triangle of brickwork above
- Bedroom above
Loads:
- Masonry: ~4 kN/m
- Minimal floor loads (joists don’t bear on wall)
- Total: ~4-5 kN/m
Beam: 203×133×25 RSJ
- Cost: £255-330 (3.8m length)
- Capacity: ~8-10 kN/m at 3.5m (adequate safety margin)
Medium Knockthrough (3.5-4.5m)
Typical scenario: 1930s semi-detached, living room to dining room
Configuration:
- Span: 4.0m
- Cavity wall construction
- Floor joists perpendicular (span 2.5m onto wall)
- Two bedrooms above
Loads:
- Cavity wall: ~6 kN/m
- Floor dead load: 0.6 kN/m² × 1.25m = 0.75 kN/m
- Floor live load: 1.5 kN/m² × 1.25m = 1.88 kN/m
- Total: {8.6 kN/m
Beam: 203×133×30 RSJ
- Cost: £350-450 (4.3m length)
- Capacity: ~8-9 kN/m at 4m (adequate)
- Or 254×146×31 for better deflection control
Large Knockthrough (4.5-6m)
Typical scenario: New build, kitchen-dining-living open plan
Configuration:
- Span: 5.5m
- Timber frame with brick facing
- Complex roof loads above
- Multiple rooms combined
Loads:
- Walls and roof: ~10-12 kN/m
- Floor loads: 6-8 kN/m
- Total: ~18 kN/m
Beam: 305×165×40 UB
- Cost: £550-720 (5.8m length)
- Heavy beam requires crane/mechanical lifting
- Professional installation essential
Step-by-Step Installation
Phase 1: Design and Approval (Weeks 1-4)
Week 1: Engage structural engineer
- Site visit and assessment
- Discuss design intentions
- Identify services
- Fee: £350-600
Week 2: Engineer produces design
- Calculates loads
- Specifies beam size
- Details padstones and supports
- Provides drawings
Week 3: Building Control application
- Submit engineer’s calculations
- Floor plans showing alteration
- Specification of materials
- Fee: £220-400
Week 4: Await approval
- Review period
- May require clarifications
- Approval certificate issued
Phase 2: Preparation (Week 5)
Order materials:
- RSJ beam (lead time 1-2 weeks)
- Padstones (pre-cast or materials)
- Acrow props and strongbacks (hire or buy)
- DPC membrane
- Fire protection materials
Prepare site:
- Clear rooms both sides
- Protect floors and furniture
- Arrange skip for debris (£150-250)
- Set up dust barriers
Relocate services:
- Electrician rewire circuits
- Plumber reroute pipes
- Confirm all services clear of work area
Phase 3: Install Temporary Support (Week 6, Day 1)
Critical safety step - see comprehensive guide in related article
Below opening:
- Place strongbacks perpendicular to joists
- Position acrow props (typically 4-6 props for 4m opening)
- Progressively load props until fully supporting structure
Above opening (if required):
- Install needles through wall
- Support needles on props each side
- Transfer load from wall to needles
Building Control inspection: Verify temporary works adequate
Phase 4: Demolition (Week 6, Day 2-3)
Mark out opening:
- Use engineer’s dimensions exactly
- Mark plumb lines for verticality
- Identify padstone positions
Remove plaster/finishes:
- Both sides of wall
- Extend 300mm beyond opening each side
- Reveal structure beneath
Cut masonry:
- Score cutting lines with angle grinder
- Cut vertically at sides of opening
- Cut horizontally at top (leave temporary support of brickwork above)
- Work from top down within supported area
Remove bricks/blocks:
- Carefully remove masonry
- Keep rubble for filling/disposal
- Clean out mortar and debris
Create padstone recesses:
- Each end of opening
- Depth: Padstone thickness + 10mm mortar
- Width/length per engineer’s specification
- Clean and level base
Phase 5: Install Padstones (Week 6, Day 3-4)
Prepare:
- Clean recesses thoroughly
- Dampen (not saturate) concrete surfaces
Mortar bed:
- 10mm thick 1:3 cement:sand mix
- Level carefully with spirit level
- Work quickly before setting
Set padstones:
- Lower into position
- Press into mortar bed
- Level in all directions
- Critical: Both padstones must be exactly same height
- Allow 24-48 hours curing
DPC layer:
- Bitumen felt or plastic membrane
- Prevents moisture transfer to steel
Building Control inspection: Padstones before beam installation
Phase 6: Beam Installation (Week 7, Day 1)
Beam preparation:
- Apply rust-inhibiting primer if not pre-treated
- Mark bearing positions
- Attach lifting straps/equipment
Lifting:
Light beams (<100kg):
- 3-4 strong people can manually lift
- Coordinated lifting on count
- Careful maneuvering through opening
Heavy beams (>100kg):
- Engine crane (hire £60-100/day)
- Block and tackle system
- OR hire professional riggers
Positioning:
- Lift into opening
- Rest on padstones
- Verify 100mm+ bearing each end
- Check level (critical for floors above)
- Add steel packing shims if needed (never wood)
Temporary support:
- Add props directly under beam ends
- Keep all existing temporary support in place
- Don’t release until making good complete
Phase 7: Make Good Above Beam (Week 7, Day 2-3)
Install permanent support above:
- May be concrete lintel
- Or rebuild masonry directly on beam
- Follow engineer’s specification
Rebuild masonry:
- Strong mortar (1:3 or 1:4)
- Good bond to existing
- Tooth into existing brickwork
- Leave weep holes if external wall
Curing period:
- Minimum 7 days before removing temporary support
- 14 days preferred
- Check weather (avoid freezing conditions)
Phase 8: Remove Temporary Works (Week 8)
After adequate curing:
Progressive release:
- Release props quarter-turn each
- Work systematically across all props
- Pause 10-15 minutes between rounds
- Observe for movement/cracking
- Repeat until all props unloaded
Remove equipment:
- Dismantle props and strongbacks
- Remove needles (if used)
- Fill needle holes
Final check:
- No visible deflection
- No cracks developed
- Beam remaining level
Building Control final inspection
Phase 9: Finishing (Weeks 9-10)
Below beam:
- Box in with plasterboard (fire protection if required)
- OR leave exposed for industrial aesthetic
- Skim plaster to match existing
- Paint/decorate
Floor repair:
- Make good where props stood
- Level with existing floor
- Replace flooring
New features:
- Install spotlights if planned
- Built-in shelving
- Different flooring in zones
Final decoration:
- Paint throughout
- Install skirting
- Ceiling cornice/details
Cost Breakdown Example
Typical 4m knockthrough project (UK 2026):
| Item | Cost |
|---|---|
| Professional fees | |
| Structural engineer | £380-580 |
| Building Control | £250-380 |
| Materials | |
| RSJ beam (203×133×30, 4.3m) | £340-430 |
| Padstones (2) | £75-120 |
| Acrow props hire (4, 3 weeks) | £150-240 |
| Strongbacks, boards, fixings | £80-130 |
| Skip hire | £150-230 |
| Fire protection | £60-120 |
| Plasterboard and materials | £120-200 |
| Labour (if hiring) | |
| Services relocation | £500-900 |
| Beam installation | £800-1,400 |
| Plastering/finishing | £400-750 |
| Decoration | £350-650 |
| Total (professional install) | £3,655-6,130 |
| Total (supervised DIY) | £2,405-3,090 |
Value added to property: £8,000-15,000 (typical London/SE)
Design Ideas for Knocked-Through Spaces
Floor Level Changes
Create visual zones:
- Raised dining area (1-2 steps up)
- Sunken lounge (1 step down)
- Cost: £800-1,500 additional
Benefits:
- Defines spaces without walls
- Adds architectural interest
- Can conceal services under raised areas
Partial Height Walls
Retain lower section of wall:
- 1.0-1.2m height
- Creates breakfast bar/serving hatch
- Hides services and storage
- Retains some separation
Beam exposed above:
- Industrial aesthetic
- Paint/polish exposed steel
- Feature lighting
Column Features
Instead of full-width beam:
- Steel columns at 1/3 and 2/3 points
- Shorter beam spans between columns
- Creates archway effect
- Columns can be boxed decoratively
Cost: Similar to single beam, butmore architectural impact
Building Regulations Compliance
Structural (Part A)
- Structural engineer calculations (mandatory)
- Adequate beam size and supports
- Proper temporary works during installation
- Building Control inspections
Fire Safety (Part B)
If beam creates new escape route:
- May require fire protection
- 30-minute rating typical
- Intumescent paint or plasterboard boxing
Existing escape routes:
- Usually no additional requirements
- Check with Building Control
Sound Insulation (Part E)
Single dwelling:
- Usually not affected by knockthrough
Flats/conversion:
- May require acoustic treatment
- Particularly if altering party walls
Ventilation (Part F)
Combining rooms may require:
- Additional ventilation
- Larger extractor fans in kitchen
- Check Part F compliance
Energy Efficiency (Part L)
If altering external wall:
- Maintain/improve insulation
- U-value compliance
- Thermal bridging at beam
Common Problems and Solutions
Problem 1: Services in wall
Discovery: Pipes/cables running through wall to be removed
Solution:
- Identified during survey (should be known before starting)
- Reroute before demolition
- Cost: £300-800 depending on complexity
Prevention: Thorough survey before work
Problem 2: Beam won’t fit through door
Cause: Beam length exceeds door/stair width
Solutions:
- Pass through window (remove window temporarily)
- Crane lift to first floor then lower through ceiling opening
- In extreme cases, cut external hole in wall
Prevention: Plan delivery route during design phase
Problem 3: Uneven floor levels
Discovery: Floors either side of wall not level
Causes:
- Settlement over time
- Different construction periods
- Previous alterations
Solutions:
- Level with screed/self-leveling compound
- Build up lower side with additional flooring layers
- Accept slight step (threshold bar)
Cost: £200-800
Problem 4: Cracking after beam installation
Minor hairline cracks:
- Normal settlement
- Fill after 2-3 months when stable
- Not structural concern
Progressive/widening cracks:
- Potential structural issue
- Contact engineer immediately
- May indicate inadequate support or foundation issues
Professional vs. DIY
Realistic DIY scope:
You CAN do:
- Demolition (under supervision, with proper temporary support)
- Finishing plasterwork
- Decoration
- Floor repairs
You should NOT DIY:
- Structural engineering (illegal without qualifications)
- Beam installation without experience (safety risk)
- Building Control application/liaison (technical knowledge required)
- Electrical work (qualified electrician only)
- Gas work (registered engineer only)
Recommended approach:
- Hire engineer for design (essential, £350-600)
- Hire experienced builder for structural work (£1,500-2,500)
- DIY finishing to save money (£800-1,500 savings)
Total cost: £2,900-4,700 (vs. £4,000-6,000 fully professional)
Conclusion
Knocking through a wall to create open-plan living is a transformative project that adds value and improves lifestyle. Proper planning, structural engineering, appropriate beam selection, and Building Regulations compliance ensure a safe, successful outcome.
Success factors:
- Engage structural engineer - non-negotiable
- Obtain Building Control approval - before any work
- Use adequate temporary support - safety critical
- Select correct beam size - don’t undersize to save money
- Allow proper curing times - don’t rush
- Professional installation for structural work - worth the cost
Budget £3,500-6,000 for typical 4m knockthrough with professional structural installation and DIY finishing.
Value added: £8,000-15,000 - excellent ROI making this one of the best home improvements.
Disclaimer: This guide provides general information only. All structural work requires design by a chartered structural engineer and Building Regulations approval. Never undertake load-bearing structural alterations without professional involvement.